Van Sickle Junction Phase 2, part 1

The weekend of June 22, 2024 found our track crew working on Phase 2 of our Van Sickle junction rebuild project.

This was the first project that we scheduled for night time work, in an effort to avoid the daytime heat here in Florida. With some good worklights, the project came together well and it was definitely much more comfortable!

This portion of the project entails realigning the A1, A2, and A3 tracks as well as the yard ladder on the east end of the yard. Much of this track was some of the first installed on this property in the 1990s. Next week we will complete the project with the ladder track replacement and the last two new switches to be installed.